Bridge Strengthening Works – York Road Fly-Over, Leeds City Centre

Structures

The existing fly-over parapets required strengthening. They were demolished using hydro-demolition techniques and re-cast as per the existing profile. Ancillary civils works were then carried out during the parapet programme.

ScopeĀ of works:

  • Removal of the existing parapet steel railings
  • Drilling dowels and fixing reinforcement for the new parapet bays
  • To erect parapet shutters and new parapet bays
  • Removal and replacement of all kerbs across the fly-over
  • New drainage to the fly-over deck and refurbishment of the existing gullies
  • Removal and subsequent re-surfacing of the footpaths and associated slip-road verges
  • Removal of all hydro-demolition debris from scaffolding off-site to licensed facilities
  • Indepth supplied all management, labour, plant and materials for the project.